Fire Prevention |
 |
Non-flammable materials specified for use for base building and fit-out work throughout building. The tenants’ interior fit-out work must also use non-flammable materials. |
 |
Firewalls, shutters and protective wall fillings divide building into discrete fire zones. |
 |
Air conditioning automatically cut off where smoke detected.
|
| |
|
| |
Fire Detection
|
 |
Addressable detectors distributed throughout building continuously take air samples to detect unusual fog. |
 |
CCTV cameras in tower are also used for fire monitoring.
|
| |
|
| |
Fire Fighting
|
 |
Automatic sprinkler system throughout building. Basement and mechanical floor are equipped with water tanks. |
 |
The mechanical floor water tank is driven by gravity so that power failure does not interrupt water supply. |
 |
Each floor is equipped with fire hydrants and fire extinguishers, and parking lot uses foam fire extinguishers. |
 |
Transformer and power generator rooms is protected by CO2 and FM-200 gases.
|
| |
|
| |
Evacuation
|
 |
Pressurized corridors on two sides of each floor and pressurized staircases provide emergency evacuation routes. |
 |
Two fireproof refuge rooms on each mechanical floor on every 8 levels, which are connected by an outdoor refuge balcony, except for the refuge rooms on 25F. |
 |
The refuge rooms are equipped with CCTV monitor, emergency phone, water and emergency kit. |
 |
Office floors and key escape routes are protected by smoke exhaust system. |
 |
Fireman’s lifts serve from basement to the top floor. |
| |
|